Modernization of units 1 and 2 at Syrdarya TPP
Sirdaryo IES JSC
Scope of work
Modernization of units 1 and 2: replacement of the 300 MW turbine flow path, stator and rotor windings, part of the boiler heating surfaces, 0.4 and 6 kV electrical equipment, 220 kV breakers and pumps; process control system installed.
- Period
- 2014–2015
- Customer
- Sirdaryo IES JSC
- Site
- Syrdarya region, Shirin
- Role
- General subcontractor
- Status
- Completed